Aerial view of the East Toba powerhouse construction site
|

Aerial view of the Montrose powerhouse centre image site preparations
|

As of the end of January/09, 109 of 225 barge loads have been delivered to Toba.
|

Bridge construction
|

Bridge construction
|

Bridges, old and new in the Toba Valley
|

Carpentry crew
|

Carpentry crew
|

Carpentry crew
|

Carpentry crew
|

construction at the East Toba powerhouse site
|

East Toba Penstock grinding mitred elbow welds
|

East Toba penstock in trench
|

East Toba penstock positioned in trench
|

East Toba runner pit roof slab reinforcement
|

East Toba unit 1 transformer on a flatbed ready to start its trip north from Mexico.
|

Excavating for transmission line poles.
|

Generation infrastructure continues to arrive at site East Toba turbine distributor
|

Helicopter slinging in conduit to line the excavated power pole holes.
|

In remote access areas, excavation for the transmission line poles must be done by hand.
|

Installing rebar for the Toba tailrace
|

Kiewit carpentry crew
|

Kitchen serves 290 workers
|

Kitchen staff talk with Jay Yule (centre), MP John Weston (2nd from right), and Bruce Ripley, President of Plutonic Power (right)
|

Minister Raitt takes a few samples for the flight back.
|

Montrose transformer at Toba
|

Owner's Site Construction Manager, Corey Dennis
|

Penstock clearing, Montrose
|

penstock stockpile yard in the Toba Valley
|

Pouring concrete for the Toba powerhouse base
|

Procurement of the generating equipment is progressing well with many pieces on their way from suppliers in Spain, China, Romania, France, Germany, Mexico and other locales.
|

Pumping concrete for the Toba tailrace
|

Re-commissioning the old logging roads in the Toba Valley
|

Reinforcing bar in East Toba powerhouse
|

stringing sock line to pull the conductor approximately 70km of the 3 phase conductor is in place
|

the first 4km of the transmission line strung near Freda Lake
|

The Honourable Lisa Raitt, Minister of Natural Resources Canada (left), John Weston, Member of Parliament for West Vancouver-Sunshine Coast- Sea to Sky Country (2nd from right) and Jay Yule, Superintendent of Schools, SD#47, Powell River (right) are pictu
|

The Toba diversion was completed and put into service in November/08
|

To the end of January, 51% of the planned excavation and haulage for the Montrose penstock alignment has been carried out. Excavation continues at the powerhouse site as well.
|

To the end of January, 578 of 1725 wooden pole transmission structures have been installed, and 10.5 kms of transmission line has been strung.
|

To the end of January, 578 of 1725 wooden pole transmission structures have been installed, and 10.5 kms of transmission line has been strung.
|

To the end of January, 68% of the planned excavation and haulage for the Toba penstock alignment has been carried out.
|

Toba Camp
|

Toba Camp looking SW, Toba Valley
|

Toba powerhouse base
|

wooden pole transmission line
|
|
|