Photos - April 09 Update
Email 'April 09 Update' item to a friend
Show printable version of 'April 09 Update' item in a New Window

Feedback Form

Aerial view of the East Toba powerhouse construction site

Aerial view of the Montrose powerhouse centre image site preparations

construction at the East Toba powerhouse site

East Toba Penstock grinding mitred elbow welds

East Toba penstock in trench

East Toba penstock positioned in trench

East Toba runner pit roof slab reinforcement

Generation infrastructure continues to arrive at site East Toba turbine distributor

Montrose transformer at Toba

penstock stockpile yard in the Toba Valley

Reinforcing bar in East Toba powerhouse

stringing sock line to pull the conductor approximately 70km of the 3 phase conductor is in place
 © 2010 Plutonic Power Corporation. All rights reserved. All material used and displayed on this website, including but not limited to photographs, videos, text, graphics and images ("Content") is the property of Plutonic Power Corporation or its suppliers. All Content is protected under Canadian and international copyright laws and treaties. You may temporarily download Content for personal transitory viewing, provided that: (a) use of the Content is for informational and non-commercial personal use only and no Content may be copied or posted on any network computer, used for public display or broadcast in any media, and (b) no modification of any Content is made. The reproduction, distribution, performance, display, retransmission, broadcast, modification, dissemination, and any use other than non-commercial, non-public personal use, of any Content is expressly prohibited without the prior written permission of Plutonic Power Corporation. To inquire about the use of any Content on this website, please contact us @ 604-669-4999 or info@plutonic.ca.