East Toba unit 1 transformer on a flatbed ready to start its trip north from Mexico.
|
|

Procurement of the generating equipment is progressing well with many pieces on their way from suppliers in Spain, China, Romania, France, Germany, Mexico and other locales.
|
|

To the end of January, 578 of 1725 wooden pole transmission structures have been installed, and 10.5 kms of transmission line has been strung.
|
|

To the end of January, 578 of 1725 wooden pole transmission structures have been installed, and 10.5 kms of transmission line has been strung.
|
|

Helicopter slinging in conduit to line the excavated power pole holes.
|
|

In remote access areas, excavation for the transmission line poles must be done by hand.
|
|

Excavating for transmission line poles.
|
|

To the end of January, 51% of the planned excavation and haulage for the Montrose penstock alignment has been carried out. Excavation continues at the powerhouse site as well.
|
|

To the end of January, 68% of the planned excavation and haulage for the Toba penstock alignment has been carried out.
|
|

Toba powerhouse base
|
|

Pouring concrete for the Toba powerhouse base
|
|

Pumping concrete for the Toba tailrace
|
|

Installing rebar for the Toba tailrace
|
|

As of the end of January/09, 109 of 225 barge loads have been delivered to Toba.
|
|

The Toba diversion was completed and put into service in November/08
|
|