
East Toba powerhouse with penstock trench climbing the hill in the background. The East Toba River waterfall is seen top right.
|
|

East Toba powerhouse with turbine housing stage 2 slab in place. At top left, two cranes support the first penstock section being welded to the bifurcation (water splitter) section that enters the powerhouse.
|
|

This image shows the progress made at the East Toba powerhouse between our June and July documentation photos.
|
|

The bifurcation pipes in the East Toba powerhouse.
|
|

The first penstock section out of the East Toba powerhouse being welded into place.
|
|

A welder at the mouth of the penstock.
|
|

Biurcation (green) and penstock (yellow) sections are carefully aligned by the crane operators for welding.
|
|

The steel walls of these pipes are 54mm (more than 2 inches) thick to withstand the incredible pressure of the water about to hit the turbines. It takes 14 welding passes to complete a seam.
|
|

Flying from the East Toba powerhouse up to the intake, the completed penstock sections can be seen in the trench awaiting cover.
|
|

The East Toba intake is progressing as scheduled.
|
|

A worker ties some of the miles of re-bar.
|
|

Looking north in the direction of the penstock alignment.
|
|

Formwork for the transition section from the East Toba diversion into the penstock.
|
|

The Montrose intake, looking west to the penstock alignment.
|
|

Workers at the Montrose intake have made remarkable progress. At the time of our June documentation, this site was still bare rock.
|
|

The Montrose intake.
|
|

All workers on site wear regulated safety equipment at all times, including high visibility vests, eye protection, gloves, CSA approved steel toe boots, long sleeves and pants.
|
|

In late July, the sun was out and temperatures were in the 30's C, so a few of the workers improvised some extra protection.
|
|

The Montrose penstock alignment.
|
|

The Montrose penstock alignment, looking west towards the powerhouse site.
|
|

At top of photo, a riparian repair of old logging damage is visible. The upgraded, historic forestry road parallels the transmission line right-of-way which was cleared less than two years ago. The ROW is greening up well.
|
|

Contractors are continuing to erect poles for the transmission line all along the corridor.
|
|

Careful planning of the transmission corridor allowed us to use existing logging access roads and pass through existing logging cuts. You can see a continuation of our transmission corridor cresting the ridge.
|
|

In a few locations, steel structures are necessary to support the transmission line. They represent less than 1% of the transmission pole structures carrying the line.
|
|

The transmission line turns a corner.
|
|

The transmission heading down the Freda Valley.
|
|
|